CONSTRUCTION UPDATE
Anticipated Project Schedule
|
Start: January 19, 2009
|
100% Construction |
|
Documents/Bid Documents to printer. (Send to Health Dept./Building Dept. for permitting/review.)
|
|
January 21, 2009
|
Out to bid. |
|
March 25, 2009
|
Bids due back. |
|
March 26, 2009
|
Ground Breaking. |
|
April 2, 2009
|
Award Project |
|
May 2010
|
End Construction |
|
June 2010
|
Grand Opening |
Construction Update - January, 2010

Construction Update - Nov. 20th, 2009

Construction Update - Nov. 9th, 2009

Construction Update - Oct. 20th, 2009

Construction Update - Sept. 14th, 2009

Construction Update - Sept. 8th, 2009

Construction Update - August 28th, 2009


Construction Update - August 18th, 2009

Construction Update, 'Aquatic Center Building' - August 14th, 2009

Construction Update - August 6th, 2009 by Chuck Lemberger

Construction Update - July 24th, 2009
Construction Update - July 10th, 2009 - next three photos:



Pouring Concrete for Lazy River - July 1, 2009

Construction Progress - June, 2009