| Estimated Street Costs |
Note: All costs are general cost guidelines. More detailed construction estimates are to be provided by the Engineering Department. |
| Sanitary Sewers |
$22.00 (maximum as per Municipal Code Chapter 7.276(1)(f) per lineal foot of frontage per side. |
| Storm Sewers |
$25.00 - $30.00 per lineal foot of frontage per side - Municipal Code 7.276(3). |
| Sanitary Laterals |
Approximately $1,500 for each service based on Bids. |
| Storm Sewer Connection Charge |
$500 per connection - Municipal Code Chapter 7.276(2) see note 1 |
| Watermain |
$20.00 per lineal foot of frontage per side (if petition is signed by more than 50% of property owners). |
| Water Lateral |
Approximately $1,500 for each service based on Bids. (1" copper) |
| Grading/Graveling |
$25.00 - $30.00 per lineal foot of frontage per side. |
| Concrete Paving |
$55.00 per lineal foot of frontage per side. Normally occurs 2-3 years after grading/graveling. |
| Concrete Sidewalks |
New Construction 4 ' Wide - $12/LF |
| New Construction 5' - 4" Wide - $15/LF |
| Remove & Replace 4 ' Wide - $16/LF |
| Remove & Replace 5' - 4" Wide - $21/LF |
| Inspection Fees |
Varies per subdivision - Municipal Code Chapter 21.06(2)(d)8. Currently not to exceed $5.00 per lineal foot. |
|
|