For more detailed construction costs contact the City Engineering Department at 920-686-6910.
Revised March, 2010

Estimated Street Costs Note: All costs are general cost guidelines. More detailed construction estimates are to be provided by the Engineering Department.
Sanitary Sewers $22.00 (maximum as per Municipal Code Chapter 7.276(1)(f) per lineal foot of frontage per side.
Storm Sewers $25.00 - $30.00 per lineal foot of frontage per side - Municipal Code 7.276(3).
Sanitary Laterals Approximately $1,500 for each service based on Bids.
Storm Sewer Connection Charge $500 per connection - Municipal Code Chapter 7.276(2) see note 1
Watermain $20.00 per lineal foot of frontage per side (if petition is signed by more than 50% of property owners).
Water Lateral Approximately $1,500 for each service based on Bids. (1" copper)
Grading/Graveling $25.00 - $30.00 per lineal foot of frontage per side.
Concrete Paving $55.00 per lineal foot of frontage per side. Normally occurs 2-3 years after grading/graveling.
Concrete Sidewalks New Construction 4 ' Wide - $12/LF
New Construction 5' - 4" Wide - $15/LF
Remove & Replace 4 ' Wide - $16/LF
Remove & Replace 5' - 4" Wide - $21/LF
Inspection Fees Varies per subdivision - Municipal Code Chapter 21.06(2)(d)8. Currently not to exceed $5.00 per lineal foot.

Sanitary Sewer Connection Fee

Current Pricing
Single Family/ Manufactured Home
$ 1,000
Two Family
$1,000/unit
Apartment/Multiple Family
$1,000/unit
Commercial Building
$1,500
Industrial Building
$2,500

Note 1: Storm Sewer Connection Charge is not applicable if property owner has already paid for a Storm Sewer Assessment.