The project area extends from County R to Maritime Drive. The purpose of the project is to address the deteriorating pavement structure that has reached the end of its service life, and to evaluate safety improvements along the corridor.  

Project Schedule


2019 - Reconstruction from Memorial Drive to North 14th Street.  Project is being re-bid on March 12th, 2019.  Tentative meeting with residents and contractors on March 25th from 5:00 to 7:00 p.m. or March 26th from 5:00 to 7:00 p.m. in the Council Chambers at City Hall, 900 Quay Street, Manitowoc, WI.

CONSTRUCTION START DATE:  APRIL 2019

​WALDO BLVD PROJECT  - 14TH STREET TO MARITIME DRIVE

CONSTRUCTION UPDATE MEETING 3/26/2019


Public Comments


We encourage you to review the documents below. If you have any questions or need information in the future, you may contact the WisDOT or City of Manitowoc Project Managers listed below:

Contacts

  1. Brian Haen, PE
    WIDOT Project Manager
    944 Vanderperren Way
    Green Bay WI 54304-0080
    (920) 366-4788
    Email
    Troy Robillard, PE
    Ayres Associates
    3376 Packerland Drive
    De Pere, WI 54115
    (920) 498-1200
    Email
    Dan Koski, PE
    City of Manitowoc
    900 Quay Street
    Manitowoc, WI 54220
    (920) 686-6910
    Email