2023 CONSTRUCTION PROJECTS
CTH R/NORTH RAPIDS ROAD
Property Information Meeting Letter
WS-23-1 Concrete Paving (Reed Avenue- N 8th to 500' +/- East of N 2nd Street & E. Albert Drive- Johnston to 800' East):
REED AVE - N 8TH TO 500' +/- EAST OF N 2ND STREET
Start Date: May 30, 2023
Completion Date: October 27, 2023
One-Way Traffic ONLY (Eastbound)
Northside of Road reconstruction completed first. Utilities during June, Grade, Gravel and Paving in July.
Southside of Road Reconstruction will begin the week of August 28th. Utilities at end of August, early September. Grade, Gravel and Paving in September and October.
Access to N. 2nd, N. 3rd, N. 4th & N. 5th at all times.
STREET SWEEPING PARKING BAN MAP
ALTERNATE ROUTES FOR REED AVENUE
E. ALBERT DRIVE - JOHNSTON TO 800' EAST
Estimated Start Date: June 26, 2023
Completion Date: July 28, 2023
Road Closed to Traffic - E. Albert Drive work has been completed.
WS-23-4 Asphalt Paving I
Division Street - S 9th to S 14th Street Reconstruction
Start Date: May, 2023
Completion Date: August 25, 2023
Road closed to traffic
STREET SWEEPING PARKING BAN MAP
Mariner's Trail and Bayshore Drive Trail have already been completed.
WS-23-11 Asphalt Paving II
North Leg Lincoln Park Roadway - Zoo Parking Lot to Cabin #2.
Start Date: July 5, 2023
Completion Date: Week of August 14, 2023
Alley #12, #18 and #22
Start Date: August 21, 2023
Complete Date: September 8, 2023
Evergreen Cemetery
Start Date: August 14, 2023
Completion Date: August 25, 2023
WS-23-10 21st Street Bridge over Manitowoc River - Deck Patching & Sealing
Deck Patching
Start Date: June 12, 2023
Completion Date: June 23, 2023
Deck Sealing
Start Date: Late July
Completion Date: Work completed - except for pavement markings, i.e. lane lines.
Lane Closures Only
WU-23-8 Sanitary Sewer Construction
S. 16th Street - Peninsula
Start Date: June 12th or 19th
Completion Date: July 7, 2023
Nagle Ave - N. 16th to RR Tracks
Fairmont Lane at N. 12th Street, South 11th Street (2200 Blk) Viebahn Street (1600 Blk)
Estimated Start Date: July 10, 2023
Completion Date: Project is Complete.